    Machine Base Plate Grouting: Why Epoxy Grout Was the Right Choice for a Forging Press

    Every heavy machine in a plant, whether a forging press, a compressor, a turbine or a crane rail, stands on a thin layer of material most people never see: the grout between its steel base plate and the concrete foundation. That layer is only a few centimetres thick, yet it decides whether the machine stays aligned or starts working itself loose. When a grout shrinks, cracks, absorbs oil or tires under vibration, the machine does not fail on the first day. It fails slowly: a hairline void under the plate, then rocking, then loose bolts, then misalignment, then an unplanned shutdown.

    This article explains how a real base plate grouting job at a forging plant was specified, why a free-flow epoxy grout, Armstrong's RAPIDSTRONG GROUT EP 403, was the right system for it, and how to make the same decision and do the work on your own machine foundation. It is written for plant engineers, maintenance heads, civil consultants and contractors who need to choose a grout once and get it right.

    What a machine base plate grout actually has to do

    A base plate does not sit directly on concrete. The foundation is never perfectly flat, so the plate is levelled on packers or jacking bolts, which leaves a gap. The grout fills that gap and does four jobs at the same time:

    • It transfers the load. Every kilogram of the machine, and every impact or vibration it produces, must pass through the grout into the foundation. Any void means the load travels through a smaller area and concentrates on the points still in contact.
    • It locks the alignment. The grout holds the plate where it was levelled. If it shrinks or creeps, the plate settles and the machine drifts out of alignment.
    • It damps vibration. A fully bonded, rigid grout layer stops the plate from working against the concrete.
    • It survives the shop floor. Under a working machine the grout meets lubricating oil, coolant, grease and wash-down water. A grout that absorbs these breaks down from the edges inward.

    Five failure modes account for most grout problems on site: shrinkage, which leaves voids; creep under sustained load; fatigue under repeated impact; chemical attack from oil and spillage; and incomplete filling, when the grout cannot flow all the way under the plate. Choosing a grout is really choosing which of these five risks the foundation can afford to carry.

    The project: a forging plant and a confined 30 mm gap

    The job was the grouting of a heavy machine's base plate at a forging plant. Harikarthika Engineering, Armstrong's main applicator and distributor, carried out the work with Armstrong Chemicals' materials. Three conditions defined the specification:

    A confined 30 mm gap

    About 30 mm on average under the plate. Deeper than the 10 mm a resin-only grout is made for, and far too thin and enclosed for a trowelled mortar to fill reliably.

    A forging environment

    A forging press does not put a steady load on its foundation. It hammers it, thousands of times a day, and lubricating oil and quench spillage reach the base.

    A machine that cannot sit idle

    Every day spent waiting for the grout to gain strength is a day of lost production.

    Those three conditions point to one family of materials, and within that family, to one mix.

    Why epoxy, and not cement-based grout, for this foundation

    Cement-based non-shrink grouts have a long record in general machine bedding. Armstrong's RAPIDSTRONG GROUT POWDER (GP2) is a non-shrink cementitious precision grout (BS 1881 Part 116, ASTM C1107) rated for 5–25 N/mm² of cyclic load over 2 million cycles. For the everyday machine base it is a proven choice.

    The question is always the fit to the site. Where a foundation carries constant vibration, impact and repeated oil or chemical exposure, a cement grout has two characteristics that work against it: it is porous, so it takes up oil and aggressive liquids, and it is stiff under constant dynamic stress. An epoxy grout resists oil, grease and fats, bonds to both steel and concrete, and RAPIDSTRONG GROUT EP 403 is made for low creep under sustained load.

    That is why Armstrong recommends RAPIDSTRONG GROUT EP 403 where the base plate faces constant vibration or chemical exposure: forging shops, steel works, refineries, electroplating works, chemical plants, turbine halls and crane-rail foundations.

    Condition at the foundationCement precision grout (GP2)Epoxy free-flow grout (EP 403)
    General machine bedding, moderate vibrationWell suitedSuitable
    Constant heavy impact or reciprocating loadWithin its rated cyclic loadMade for repeated dynamic load, with low creep
    Oil, grease, coolant or chemical spillageNeeds protecting from itResists oil, grease, fats, mild acids and alkalis
    Strength to get the machine back quickly67–70 N/mm² at 28 days72 N/mm² at 1 day (1 : 3 mix)
    Tight, confined gap under a large plateFlowable mix pours wellLow viscosity, flows deep into tight gaps
    Surface at the time of pouringConcrete damp, no standing waterConcrete and steel dry

    What RAPIDSTRONG GROUT EP 403 is

    RAPIDSTRONG GROUT EP 403 is a two-component, low-viscosity, free-flow epoxy grout conforming to ASTM C-881. It is made to fill the gap between the base plates of industrial installations and their foundations, under moving and dynamic loads, where spillage of chemicals, acids and alkalis is a real possibility.

    Its defining feature is that it is one system with three mixes, chosen by the thickness of the gap:

    Gap thicknessMix by weightWhat goes inCompressive strength
    0.1 to 10 mm1 : 0.5Resin and hardener only, a free-flowing liquid for fine gaps28 N/mm² at 1 day, 50 at 3 days, 72 at 7 days
    10 to 70 mm1 : 3Resin, hardener and graded silica filler supplied by Armstrong72 N/mm² at 1 day, 82 at 3 days, 85 at 7 days
    Over 70 mm1 : 2 : 1.5Resin, hardener, filler and 10–20 mm graded aggregate supplied by Armstrong63 N/mm² at 3 days, 91 at 7 days

    This is a real practical advantage. The engineer does not switch product families as the gap changes: the same resin, the same supplier, the same technical support and the same bond to steel and concrete, scaled to the job.

    Why the 1 : 3 mix was the right match at 30 mm

    A 30 mm average gap sits in the middle of the 10–70 mm band, which is the 1 : 3 mix. Its figures (BS 6319 Part 2) show why it suits a plant that cannot afford long downtime:

    Property of the 1 : 3 mixValue
    Density2,120 kg/m³
    Compressive strength at 1 day72 N/mm²
    Compressive strength at 3 days82 N/mm²
    Compressive strength at 7 days85 N/mm²
    Pot life at 20 °C25 minutes
    Pot life at 30 °C20 minutes

    Two things stand out. First, 72 N/mm² within a single day: the foundation reaches high working strength almost at once, which shortens the wait between grouting and commissioning. Second, the strength curve is almost flat from the third day: the grout reaches nearly its full strength early and keeps it, rather than relying on a slow cure.

    For comparison, the over-70 mm mix (1 : 2 : 1.5) reaches 91 N/mm² at 7 days, the highest figure in the system.

    Seven reasons it was the right choice

    1. Non-shrink, so contact is complete. Shrinkage under a base plate creates voids, and voids concentrate load. RAPIDSTRONG GROUT EP 403 is non-shrink, so it keeps full contact and bond across the whole plate.
    2. Free-flow, so it fills the gap instead of bridging it. Low viscosity lets the grout run into every corner of a confined gap, including under large plates where a stiffer material would leave air pockets.
    3. Made for dynamic loads. Resistance to repeated dynamic load and low creep under sustained load are core properties of the product: the combination a forging press, a reciprocating compressor or a high-speed turbine needs.
    4. Resists what plants spill. Oil, grease, fats, most chemicals, mild acids and alkalis, and fresh and sea water. For solvents or concentrated chemicals, ask Armstrong's technical team before specifying.
    5. High strength early. 72 N/mm² at one day in the 1 : 3 mix shortens the time between grouting and starting the machine.
    6. Bonds to both steel and concrete. The plate and the foundation become one bearing surface, with no gap left for oil or water to work into.
    7. One system, three gap ranges, one supplier. The same product covers hairline gaps of 0.1 mm through to pours beyond 70 mm, with fillers and aggregates supplied by Armstrong and technical support from its team.

    How the work is done

    A high-performance grout still fails if the preparation or the placing is wrong. This is the sequence, from bolts to commissioning.

    A machine base plate ready for groutingSection through a machine foundation. The steel base plate sits on levelling packers above the concrete, leaving a gap. An anchor bolt runs through the plate into a resin-filled hole in the foundation. Formwork stands about 150 mm from the plate on the pouring side, with a raised head box, and about 50 mm from the plate on the far side, where air vents let air out. Grout poured from the head box flows under the plate and pushes the air out ahead of it.123456Head box: pour from this side onlyMachine on its base plateAnchor bolt set in chemical anchor groutFormwork, about50 mm from the plateAir ventsPackersUp to 150 mmGrout fills the gapConcrete foundation
    Figure 1. A levelled base plate with formwork, ready for grouting. Grout poured from the head box flows under the plate and pushes air out through the vents.
    1. Fix the anchor bolts

      Set the foundation bolts in drilled holes with RAPIDSTRONG AG, a polyester chemical anchor grout. The anchor grout holds the bolt; the base plate grout supports the plate around it, and on the same installation they often work side by side. The chemical anchoring procedure gives the steps.

    2. Level and align the machine

      Level and align the machine on its packers or jacking bolts before any grout goes in. The grout fills the gap; it does not level the machine.

    3. Prepare the surfaces

      All contact surfaces must be free of dust, oil, grease, laitance and loose material, and the concrete must be sound. Clean the concrete with air blowers and a water jet, then let it dry for epoxy grout. Shot-blast the steel free of rust: wire brushing does not reach the same standard, and the underside of the plate matters as much as the top of the foundation.

    4. Build tight formwork

      Seal the formwork with rubber strips so no grout escapes. Keep it no more than 150 mm from the plate on the pouring side, with a head box, and about 50 mm from the plate on the other sides, with air vents on the far side (Figure 1).

    5. Choose the mix by the measured gap

      Measure the actual gap after levelling, not the figure on the drawing, and match it to the table above. A 30 mm average gap means the 1 : 3 mix.

    6. Mix properly

      Pour Part 2 (500 g) slowly into Part 1 (1 kg) and mix with a slow-speed stirrer for 2 to 5 minutes, until the colour is even. Add the Armstrong filler for the mix you chose and mix until uniform. Mix only what can be placed within the pot life, 20 minutes at 30 °C for the 1 : 3 mix. In summer heat that means disciplined batching, with one crew mixing and a separate crew pouring.

    7. Pour from one side, without stopping

      Pour into the head box only, so the grout flows under the plate and pushes the air out through the vents ahead of it. Pouring from two sides traps air in the middle. Have enough material and mixed batches ready before the first pour: a break leaves a cold joint, which is exactly the weakness the grout is there to remove.

    8. Let it cure

      The minimum hardening temperature is 10 °C. Leave the grout undisturbed and dry while it gains strength; epoxy grout needs no water curing. Release the machine for commissioning on the engineer's instruction.

    Packing. RAPIDSTRONG GROUT EP 403 comes in 1.5 kg, 15 kg and 30 kg packs. Graded silica filler and coarse aggregate come in 5 kg and 25 kg bags.

    Using cement grout instead? Mix RAPIDSTRONG GROUT POWDER (GP2) with 3.76 litres of water per 20 kg bag for a flowable mix, or 3.36 litres for a pourable mix, for at least 5 minutes. Keep the concrete damp with no standing water, place within 20 minutes of mixing, and water-cure for at least 7 days. GP2 goes in one pour up to 100 mm deep; deeper than that, add 10 mm aggregate at 50 to 100% of the grout weight. The full steps for both grouts are in the machine base plate grouting procedure.

    Six mistakes that undo a good grout

    1. Using the grout to level the machine. Level first, then grout.
    2. Choosing the mix from the drawing. Measure the real gap after levelling.
    3. Wire-brushing the plate for epoxy. Shot-blast it.
    4. Pouring from two sides. Air is trapped in the middle.
    5. Mixing more than the crew can place. A half-set batch does not flow.
    6. Stopping halfway, or loose formwork. Either leaves the gap part-filled.

    Where else this grout is used

    The same product and the same reasoning apply wherever a heavy installation needs a permanent, load-bearing, chemical-resistant bed:

    • Reciprocating machinery and compressors
    • High-speed turbines and generator sets
    • Heavy crane and transporter rails
    • Testing equipment and press foundations
    • Steel works, refineries, electroplating works and chemical plants

    Choosing between grouts: a quick guide

    Armstrong's range covers the full spread of grouting work. The right product is a matter of fit, not rank:

    If the foundation itself is cracked, repair it before grouting: see the concrete crack repair guide. The machine grouting and anchoring guide covers the whole job from foundation to commissioning.

    Specification checklist for engineers

    Before you issue a base plate grouting specification, confirm each of these:

    1. The measured gap after levelling, and so the mix.
    2. What reaches the base: oil, coolant, acids, wash-down water.
    3. The load: static, cyclic, impact or reciprocating.
    4. How soon the machine is needed, which sets the strength needed at that age.
    5. The temperature at the time of pouring, which sets the batch size through pot life.
    6. The steel surface standard: shot-blasted for epoxy, not wire-brushed.
    7. Material, mixers and crew to pour without a break.
    8. Armstrong's sign-off for any solvent or concentrated chemical exposure.

    Questions and answers

    By Mr. Mohan Rao, Armstrong Chemicals Pvt Ltd, an ISO 9001:2015 certified manufacturer of construction and waterproofing chemicals, based in Bengaluru.