Industrial epoxy flooring is chosen by what the floor has to resist. For dry stores Armstrong makes ARMSTRONG LBF 350 and FL/SL 1000. For forklifts, HBF 400, with a ROOFCRETE EP screed where the slab needs one. For acids, ARC 450. For food, pharma and occupied buildings, FL SLW, LBF 350 or FL/SL 1000. For static control, FL/SL C/D. New concrete is hardened as it is cast with RAPIDSTRONG FM 90, NH 89, CFH 92 or LFH ADMIX 91. Every floor starts with a dry, sound, mechanically prepared slab.
By Armstrong Chemicals Pvt. Ltd. · ISO 9001:2015 certified · Protecting buildings, roofs and structures since 1982
People search for industrial epoxy flooring, epoxy flooring for a warehouse, a floor hardener, ESD flooring or acid resistant flooring. These are five different floors. The right one depends on what runs on the floor, what spills on it, how it is cleaned and what the concrete under it is like. Thickness and colour come after that. Six checks tell you which floor you need.
If the slab is still to be cast, a floor hardener can be worked into it on the day. If it is already cast, the choice is between coatings, toppings and overlays.
Foot traffic and trolleys, pallet trucks, forklifts or steel wheels. Heavier wheels and impact need a thicker floor or a hardened concrete surface.
Water, oils, detergents, acids or alkalis. Note the chemical, its strength and its temperature. Acid areas need an acid resistant system.
Dry sweeping, wet mopping, pressure washing or hot water and steam. Hot washdown and steam-cleaned zones are assessed case by case.
Ground floor slabs without a damp-proof membrane can carry moisture upwards. Moisture under a resin floor causes blisters and peeling. Test before you choose.
Static control for electronics and server rooms, a hygienic surface for food and pharma, low odour in an occupied building, or line marking for traffic aisles.
Match the floor to one route. Each route names the Armstrong products that suit it and takes you to the next step. Where more than one product fits, pick the one that fits the site. An Armstrong expert helps you choose.
Choose the floor by what it has to do, then prepare the slab properly. Most resin floor failures start under the coating, in the concrete, and have little to do with the product on top.
Tell us what runs on the floor, what spills on it and how it is cleaned. An Armstrong applicator or distributor will recommend a system. Toll free 1800 103 2034. Armstrong manufactures epoxy flooring chemicals and floor hardeners in Bengaluru and supplies them all across India, with South India as its major hub.
Written by the technical team at Armstrong Chemicals Pvt. Ltd., an ISO 9001:2015 certified manufacturer of construction and waterproofing chemicals in Bengaluru, with more than 200 products. Armstrong has been protecting buildings, roofs and structures since 1982 and supplies all across India, with South India as its major hub.
The methods on this page are Armstrong's standard procedures. Doses, thicknesses and the number of coats are adjusted to the conditions on each site. Load-bearing repairs and strengthening are designed by a structural engineer.
Last updated · Questions on this method: toll free 1800 103 2034
Industrial epoxy flooring is chosen by what the floor has to resist. For dry stores Armstrong makes ARMSTRONG LBF 350 and FL/SL 1000. For forklifts, HBF 400, with a ROOFCRETE EP screed where the slab needs one. For acids, ARC 450. For food, pharma and occupied buildings, FL SLW, LBF 350 or FL/SL 1000. For static control, FL/SL C/D. New concrete is hardened as it is cast with RAPIDSTRONG FM 90, NH 89, CFH 92 or LFH ADMIX 91. Every floor starts with a dry, sound, mechanically prepared slab.
By Armstrong Chemicals Pvt. Ltd. · ISO 9001:2015 certified · Protecting buildings, roofs and structures since 1982
People search for industrial epoxy flooring, epoxy flooring for a warehouse, a floor hardener, ESD flooring or acid resistant flooring. These are five different floors. The right one depends on what runs on the floor, what spills on it, how it is cleaned and what the concrete under it is like. Thickness and colour come after that. Six checks tell you which floor you need.
If the slab is still to be cast, a floor hardener can be worked into it on the day. If it is already cast, the choice is between coatings, toppings and overlays.
Foot traffic and trolleys, pallet trucks, forklifts or steel wheels. Heavier wheels and impact need a thicker floor or a hardened concrete surface.
Water, oils, detergents, acids or alkalis. Note the chemical, its strength and its temperature. Acid areas need an acid resistant system.
Dry sweeping, wet mopping, pressure washing or hot water and steam. Hot washdown and steam-cleaned zones are assessed case by case.
Ground floor slabs without a damp-proof membrane can carry moisture upwards. Moisture under a resin floor causes blisters and peeling. Test before you choose.
Static control for electronics and server rooms, a hygienic surface for food and pharma, low odour in an occupied building, or line marking for traffic aisles.
Match the floor to one route. Each route names the Armstrong products that suit it and takes you to the next step. Where more than one product fits, pick the one that fits the site. An Armstrong expert helps you choose.
Choose the floor by what it has to do, then prepare the slab properly. Most resin floor failures start under the coating, in the concrete, and have little to do with the product on top.
Armstrong makes dry shake and liquid floor hardeners, epoxy floor coatings, self-levelling epoxy toppings, acid resistant and ESD floors, and the screeds, primers and sealants that go with them. They differ by fit. Answer three questions for a starting recommendation, then confirm it with an Armstrong expert.
{{ resWhy }}
Before any product goes on, remove all loose, old and flaking material and test the slab for moisture. This is a starting point, and an Armstrong expert confirms the final choice after seeing the site.
Every product below suits this job. Pick the one that fits the site, or ask an Armstrong expert to choose with you.
An epoxy floor is only as good as its bond to the concrete. The bond depends on three things: a slab that is dry enough, a surface that is clean and mechanically roughened, and repairs that are finished before the primer goes on. Every Armstrong epoxy flooring product is applied to concrete prepared by grinding or shot blasting.
A self-levelling epoxy follows the slab. It will not hide a floor that is badly out of level. Two Armstrong products are used under a resin floor.
With ALSTRONG FSL 55, never add extra water to loosen the mix, and pass a spiked roller over the wet surface straight away to release trapped air. Blend it with a drill mixer at 400 to 500 rpm.
A resin floor that has failed tells you why, if you look before you scrape. Read the failure, fix the cause, then repair the smallest area that reaches sound material. Removing the whole floor is the extreme case.
An epoxy screed floor is a heavy-duty, chemical- and abrasion-resistant surface for drains, tank bases and industrial floors. It is a system, and each layer depends on the one before it: primer for the bond, screed for the body, topcoat for the finish. Doses, thicknesses and coats are the standard figures; the site and the exposure decide where they move.
Every Armstrong epoxy floor follows the same order. The slab is prepared, primed, levelled or screeded where needed, and finished with the coating or topping that suits the use. Joints are carried through and sealed, and the floor is left to cure before traffic.
For dry storage and light to medium duty, ARMSTRONG LBF 350 builds 200 to 400 microns in coats. For a smooth, glossy poured floor, ARMSTRONG FL/SL 1000 is laid at 2 to 3 mm. For forklift routes, impact and heavy manufacturing, ARMSTRONG HBF 400 builds 400 to 2,000 microns and can take broadcast aggregate for extra thickness and grip. All three suit this work. The traffic and the finish you want decide between them.
ARMSTRONG ARC 450 is a two-component acid resistant epoxy for floors and walls. Armstrong lists it as resistant to hydrochloric, sulphuric and nitric acid, and to the alkalis sodium hydroxide and potassium hydroxide. It is applied in 2 to 3 coats of 200 to 300 microns each, with the next coat after 12 to 16 hours. Full chemical resistance comes after 7 days. The coating is taken up the walls and plinths so a spill has nowhere to get behind it. Joints in chemical areas are sealed with ROOFEX-SEAL PS, which resists fuels, oils and dilute acids. Tell Armstrong the chemical, its concentration and its temperature before the system is fixed.
These floors need a continuous, easily cleaned surface, a cove at every wall and falls to the drains. ARMSTRONG FL SLW is a water based, low VOC self-smoothing topping laid at 1.5 to 3 mm, suited to occupied buildings where odour matters. ARMSTRONG LBF 350 is solvent free and listed for food processing and commercial kitchens. ARMSTRONG FL/SL 1000 is listed for pharmaceutical plants and clean rooms. CONPROOF EP is a food-neutral, water-dilutable epoxy coating that can be applied to damp concrete, in two coats 6 hours apart, for wet process rooms, walls and tanks. Part 1, Part 2 and clean water are mixed at 1:1:1, with a pot life of 60 minutes at 20°C. It is stated to resist fatty acids, wash chemicals and detergents, and it can be blended with cement as an epoxy patching putty. It takes light foot traffic after 16 hours and reaches full chemical cure in 7 days.
ARMSTRONG FL/SL C/D is a two-component epoxy topping made in static conductive and static dissipative grades. The concrete is prepared to CSP 3 to 4. A conductive primer goes down, a copper tape earthing grid is laid on it and connected to earth, and the topping is applied by squeegee and roller. Resistance is measured on site after application: below 1 megohm for the conductive grade, and 1 megohm to 1 gigohm for the dissipative grade. Thickness is set for each project. Allow 7 days full cure before heavy traffic.
If the slab is still to be cast, the hardest-wearing floor is often the concrete itself. A floor hardener makes the top of the slab dense and abrasion resistant. It becomes part of the concrete, so there is no film to peel. This is the usual answer to concrete floor dusting, loading bay floor damage and forklift wear on new floors.
Every product below is made by Armstrong and each suits the work listed against it. They differ by fit: thickness, chemistry and the duty they are built for. Where two or three suit your floor, pick the one that fits the site. An Armstrong expert helps you choose.
Approximate quantities for 1,000 sq.ft (about 93 sq.m), worked out from Armstrong stated figures on a smooth, prepared surface. Armstrong does not publish a coverage figure per kg for the epoxy floor toppings in the documents used here, so those rows show the volume of the finished film at the stated thickness. Use the calculator for your own floor, and ask Armstrong for pack quantities.
The litres of film are a volume, not a pack quantity.
Enter the floor size and choose the floor to see the material needed. Quantities only. Where Armstrong has not published a coverage figure, the calculator says so and Armstrong confirms the quantity.
This is an estimate of material only, worked out from each product's stated coverage on a smooth, prepared surface. Rough or porous surfaces use more, so allow about 10% extra. Crack sealing, patch repair, plaster, coving and tiling materials are not included. An Armstrong expert confirms the final quantity after seeing the site.
A two-component epoxy: a resin and a hardener mixed on site. Armstrong makes ARMSTRONG LBF 350 and ARMSTRONG HBF 400 as roller or squeegee coatings, ARMSTRONG FL/SL 1000 and ARMSTRONG FL SLW as poured self-levelling toppings, ARMSTRONG ARC 450 for acid areas and ARMSTRONG FL/SL C/D for static control. An epoxy primer goes under each, and ROOFCRETE EP is used as the screed and repair mortar.
They do different jobs. A coating is a thinner film, 200 to 2,000 microns, applied by roller or squeegee. It follows the texture of the slab. A self-levelling epoxy is poured at 1.5 to 3 mm and gives a smooth, level, glossy surface that is easy to clean. Choose a coating for stores and workshops, and a self-levelling floor for clean rooms, showrooms and pharma.
On a new slab that must resist wear, a floor hardener is usually the right start. It is part of the concrete and cannot peel. Use epoxy where the floor must resist chemicals, be hygienic, control static or look finished. Many plants use both: hardened concrete in the yard and loading bays, epoxy in process and packing areas.
For racking aisles and light trolley traffic, ARMSTRONG LBF 350. For forklift routes and turning areas, ARMSTRONG HBF 400 at a higher build. For a new warehouse slab, RAPIDSTRONG FM 90, RAPIDSTRONG NH 89 or RAPIDSTRONG CFH 92 harden the concrete as it is cast. All of them suit warehouses. The traffic decides.
Armstrong states light traffic after 24 hours for ARMSTRONG FL/SL 1000 and ARMSTRONG FL SLW, and 7 days of full cure before heavy traffic and chemical exposure for ARMSTRONG HBF 400. Plan on 7 days before forklifts unless Armstrong confirms a shorter time for your system. ALSTRONG FSL 55 takes forklifts in 5 to 7 days.
Almost always because of what is under it. The common causes are moisture in the slab, a surface that was not ground or shot blasted, oil or laitance left on the concrete, a primer that was skipped, and joints that were coated over. The epoxy itself is rarely the cause.
ESD flooring drains static charge safely to earth so it does not damage electronic parts or cause a spark. ARMSTRONG FL/SL C/D is laid over a conductive primer and a copper tape earthing grid. The conductive grade measures below 1 megohm and the dissipative grade 1 megohm to 1 gigohm. It is used in electronics plants, data centres, server rooms and operating theatres.
ARMSTRONG ARC 450. It is an acid resistant epoxy for floors and walls, applied in 2 to 3 coats of 200 to 300 microns. Full chemical resistance comes after 7 days. Give Armstrong the acid, its concentration and temperature so the system can be confirmed.
Standard epoxy floors need a dry slab. Test for moisture first and fix the source. CONPROOF EP is stated to bond to damp concrete and ROOFCRETE EP cures on damp surfaces, so they are used in the build-up for damp areas. An Armstrong expert confirms the system after seeing the test results.
Grind the high spots and fill the low ones. ALSTRONG FSL 55 is a self-levelling cementitious topping poured 6 to 12 mm thick in one pass. Each 25 kg bag is mixed with 4.75 litres of water. For heavy-duty areas, ROOFCRETE EP is trowelled as an epoxy screed over ROOFBOND EP.
Only over coating that is still firmly bonded. Everything loose, blistered or flaking is removed, the remaining surface is abraded and the cause of the failure is fixed first. Where most of the old floor is hollow, it is removed completely. Ask Armstrong before recoating over an old epoxy.
RAPIDSTRONG FM 90 and RAPIDSTRONG CFH 92 are broadcast at 6 to 12 kg per sq.m over green concrete. RAPIDSTRONG NH 89 is broadcast at 3.5 kg per sq.m for normal traffic and 6 to 12 kg per sq.m for heavy traffic. RAPIDSTRONG LFH ADMIX 91 is a liquid, dosed at 500 ml to 1 litre per 50 kg bag of cement. Higher rates give better abrasion resistance.
Yes, with the right product and details. ARMSTRONG LBF 350, ARMSTRONG FL SLW and CONPROOF EP are listed for food and beverage areas. The floor needs coves, falls to drains and a slip resistant finish in wet zones. Areas cleaned with hot water or steam are assessed case by case.
Joints in the slab are never bridged with rigid epoxy. They are cut through the floor and filled with a flexible sealant: ROOFEX-SEAL PS for chemical, fuel and traffic joints, or ROOFEXSEAL PU 212 for general floor joints. For wide structural joints see expansion joint sealing.
It depends on the build-up. Preparation and repairs come first, then primer, screed where needed and one or more topcoats, with waiting time between coats. ARMSTRONG ARC 450, for example, needs 12 to 16 hours between coats. After the last coat, allow 24 hours before light traffic and 7 days before full service.
Tell us what runs on the floor, what spills on it and how it is cleaned. An Armstrong applicator or distributor will recommend a system. Toll free 1800 103 2034. Armstrong manufactures epoxy flooring chemicals and floor hardeners in Bengaluru and supplies them all across India, with South India as its major hub.
Written by the technical team at Armstrong Chemicals Pvt. Ltd., an ISO 9001:2015 certified manufacturer of construction and waterproofing chemicals in Bengaluru, with more than 200 products. Armstrong has been protecting buildings, roofs and structures since 1982 and supplies all across India, with South India as its major hub.
The methods on this page are Armstrong's standard procedures. Doses, thicknesses and the number of coats are adjusted to the conditions on each site. Load-bearing repairs and strengthening are designed by a structural engineer.