    Micro Concrete Column Jacketing

    Cast jackets for deep repairs and strengthening

    Weak or damaged columnsBeam soffits and sidesDeep repairsCongested reinforcement
    1. The engineer fixes the propping, the extra bars and links, the jacket thickness and the grade of micro concrete.
    2. Remove loose and delaminated concrete to a sound base and treat the existing steel.
    3. Tie new bars and anchor starter bars and dowels in drilled holes with RAPIDSTRONG AG.
    4. Set up watertight formwork with a pouring point and air vents, ready to close.
    5. Brush ROOFBOND EP onto the prepared concrete, close the formwork and pour within its overlay time of 2 to 3 hours at 30°C.
    6. Mix the micro concrete with the stated water until smooth and pour or pump it from one side without a break.
    7. Strike the formwork and water-cure for 7 days.

    Retrofit the beam-column joint along with the column, or the weak point moves to the joint.

    Micro concrete is a pre-packed, free-flowing, non-shrink concrete with small aggregate. It fills tight spaces around congested steel without a vibrator.

    ROOFCRETE PMC 112About 21.92 litres per 40 kg bag
    CuringWater-cure 7 days