Treatment Procedures.
Step-by-step waterproofing, structural repair and rehabilitation methods, grouped by the chemistry they use, each mapped to the Armstrong products that carry it out. Select a treatment to view the full procedure and product recommendations.
Treatment · Strengthening & jacketing
Micro Concrete Column Jacketing
Cast jackets for deep repairs and strengthening
Applications
Weak or damaged columnsBeam soffits and sidesDeep repairsCongested reinforcement
Procedure
- The engineer fixes the propping, the extra bars and links, the jacket thickness and the grade of micro concrete.
- Remove loose and delaminated concrete to a sound base and treat the existing steel.
- Tie new bars and anchor starter bars and dowels in drilled holes with RAPIDSTRONG AG.
- Set up watertight formwork with a pouring point and air vents, ready to close.
- Brush ROOFBOND EP onto the prepared concrete, close the formwork and pour within its overlay time of 2 to 3 hours at 30°C.
- Mix the micro concrete with the stated water until smooth and pour or pump it from one side without a break.
- Strike the formwork and water-cure for 7 days.
Important Suggestions
Retrofit the beam-column joint along with the column, or the weak point moves to the joint.
Why This Treatment?
Micro concrete is a pre-packed, free-flowing, non-shrink concrete with small aggregate. It fills tight spaces around congested steel without a vibrator.
Recommended Products
Dosage & Coverage
ROOFCRETE PMC 112About 21.92 litres per 40 kg bag
CuringWater-cure 7 days
Related Solution Guides