Skip to main content
    Technical Reference

    Treatment Procedures.

    Step-by-step waterproofing, structural repair and rehabilitation methods, grouped by the chemistry they use, each mapped to the Armstrong products that carry it out. Select a treatment to view the full procedure and product recommendations.

    Treatment · Strengthening & jacketing

    Beam Jacketing with Shear Connectors

    New steel and concrete tied to existing beams and slabs

    Beams with lost sectionSlab soffits needing added steelHeritage and institutional buildings
    1. Erect scaffolding and prop each beam before any concrete is removed.
    2. Chip with pneumatic chisels to the hard parent concrete and clean with a water jet.
    3. Remove rust scale with emery paper and wire brushes, treat tight rust with ALSTRONG RC and prime the bars with ALSTRONG ZP 777.
    4. Drill holes, brush and blow them out with compressed air, and fix L-shaped 8 mm shear connectors with RAPIDSTRONG AG.
    5. Fabricate the new bars to the drawing and tack-weld them to the shear connectors.
    6. Apply ROOFBOND EP just before concreting and cast the jacket in micro concrete. On slabs, lay polymer screed concrete with ROOFCRETE AR to about 50 mm.
    7. Inject remaining cracks with epoxy and cure for at least 7 days before removing the props.

    The jacket size, connector spacing and propping all come from the structural engineer.

    Shear connectors tie the new steel and concrete to the old member so the two carry load together. Without them the jacket can separate.

    Shear connectorsL-shaped, 8 mm, to the drawing
    Polymer screed (slabs)About 50 mm average

    Need this for your project?

    Technical support and product recommendations from Armstrong's engineers. Toll free 1800 103 2034.

    Call usTalk to an expert